The duplex awaits an occupancy permit and the developer already lives in the penthouse: Magistrate's Court orders temporary compensation of NIS 30,000 a month

A Kfar Saba Magistrate's Court ordered a developer and his company to pay buyers NIS 30,000 a month pending trial, while the building still lacks an occupancy permit.

Written by AI, without human editing, based on media reports. This article is not based on the court's official document.

The duplex awaits an occupancy permit and the developer already lives in the penthouse: Magistrate's Court orders temporary compensation of NIS 30,000 a month

The spouses Amir Vitznblit, a judge at the Tel Aviv District Court, and Oren Cohen signed in June 2024 to buy a duplex at 27 Dizengoff Street in Tel Aviv for NIS 9 million. NIS 8.1 million has already been paid, and the delivery date in the contract was 18 February 2025. According to a report in ICE (ICE) dated 23 November 2026, the building still lacks an occupancy permit, some of its apartments are already occupied, including the penthouse where developer David Saban lives.

According to the couple, they wanted to move with their children into an apartment with a safe room. They claim they cannot sell their current home while the move is delayed, and their mortgage and loan payments amount to about NIS 25,000 a month.

On 19 November 2026, Judge Hagit Bolmash of the Kfar Saba Magistrate's Court issued an interim decision, not a judgment. She ordered Bereshit HaShachar Investments and Properties Ltd. and Saban, its controlling shareholder, to pay the couple NIS 30,000 a month already during the trial. The judge found that no professional documents had been presented establishing a near date for obtaining the permit. The sum was derived from an appraisal submitted by the buyers, according to which rent for a similar apartment is NIS 20,000 a month, multiplied by 1.5 under the Sale Law. The obligation was set from 20 October 2026, the date the application was filed, until an occupancy permit and delivery or another decision, and NIS 10,000 in costs was also awarded.

The payment is temporary, on account of compensation to be awarded later. The order was conditioned on the buyers' undertaking to repay the money with linkage and interest if their claim is rejected or a lower sum is awarded. The company and Saban argue that the key was handed over and the apartment is furnished, but the buyers have not paid the balance of the price. They dispute the rent estimate and claim that the buyers' complaints to the municipality and the petition they filed contributed to the delay. Saban stated that he will request leave to appeal, and according to him the court did not give sufficient weight to his arguments.

The hard question

The difficult question is whether it is right to impose a monthly payment before a ruling, when the sum rests on an appraisal by one side and responsibility for the delay and the balance of the price are in dispute. On the other hand, buyers who paid NIS 8.1 million are waiting past the contractual date, and the court found that no near date for the permit had been shown. The decision mainly concerns those awaiting delivery of an apartment and an occupancy permit, and developers who are delayed, but it is one decision in one case, and the factual disputes will still be resolved in the claim itself. Who should bear the risk until the final judgment? Comments are welcome.

Arguments that may support the decision

  • The delivery date in the contract was 18 February 2025, and in November 2026 there is still no occupancy permit, after NIS 8.1 million of the NIS 9 million price was paid.
  • The court found that no professional documents were presented establishing a near date for obtaining the permit, even though some apartments are already occupied, including Saban's penthouse.
  • The payment is temporary, on account of compensation to be awarded later, and the order was conditioned on the buyers' undertaking to repay with linkage and interest if their claim is rejected or a lower sum is awarded.

Arguments that may oppose the decision

  • The sum rests on an appraisal submitted by the buyers, and the company and Saban dispute the rent estimate.
  • According to the company and Saban, the key was handed over, the apartment is furnished, and the buyers have not paid the balance of the price.
  • They claim that the buyers' complaints to the municipality and the petition they filed contributed to the delay in obtaining occupancy.

Now you be the judge

  • Do you think justice was done?
  • Is it right to order a developer to pay monthly temporary compensation to apartment buyers before the claim is decided?
  • How should a sum of NIS 30,000 a month be set when the company and Saban dispute the buyers' appraisal?

Source

Source of the article: ICE (ICE). The article is based on media reports and not on the court file itself. This means the arguments for and against are not findings of the court.